The contractor will begin milling asphalt on 2nd Avenue South from South Bluff Blvd. to South 11th Street on Wednesday, September 2, and from South 11th Street to South 18th Street on Thursday, September 3. ‘Read more’ for the schedule of work on the project. One lane (in each direction) of 2nd Avenue South from South Bluff Blvd. to South 14th Street will be open at all times. Flaggers will control the traffic on 2nd Avenue South from South 14th Street to South 18th Street.
Beginning on Friday, September 4, the contractor will apply patches to the milled surface. Patching is expected to be completed by Thursday, September 10. Paving should begin on either Thursday, September 10 or Friday, September 11, and will take approximately 8 days.
There will be access to all residences on 2nd Avenue South during this time, however, short delays should be expected.
Please contact the Engineering Department at 563.244.3423 with any questions